Uncategorized Construction Update 7/21/22 July 21, 2022

Abatement work in the LRC and Student Center has been completed. Concrete work in Chandler Village is scheduled to begin on Tuesday, July 26. Work on the LRC sidewalk will begin once Chandler Village is complete at a date yet to be determined. Please observe all posted signs and exercise caution in active construction zones.

Read Story Construction Update 7/21/22
Uncategorized Construction Update July 7, 2022 July 7, 2022

Ostrow electrical work inside the LRC, Student Center, and vault is complete. Containment is in place for abatement work on the tile floor in the LRC electrical room. Work on the Dowden/Chandler Village courtyard will begin in late July. Please exercise caution and observe posted instructions in active work zones.

Read Story Construction Update July 7, 2022
Uncategorized Construction Update Week of 6/6 June 6, 2022

Interior electrical conduit work will continue in the Learning Resource Center (LRC) throughout the week. Bollards will be installed outside Waslayean Hall and Sullivan, and digging will commence outside the LRC. Please exercise caution in work areas and observe all posted signs.

Read Story Construction Update Week of 6/6
Uncategorized Construction Work Resumes May 26, 2022

Electrical work has resumed in the Learning Resource Center and Student Center. The week of May 30, conduits will be installed in LRC 114 and LRC 104B. In the Student Center, door replacement work is ongoing. Please exercise caution in marked work areas and follow all posted instructions.

Read Story Construction Work Resumes
Uncategorized Heavy Construction Complete until Spring November 29, 2021

The university is pleased to report that the bulk of heavy construction activity has now been completed for the winter, and will not resume again until spring 2022. There may be occasional small-scale outdoor projects in the interim, though not significant enough to disrupt traffic flows on campus. As a reminder, the campus community is […]

Read Story Heavy Construction Complete until Spring
Uncategorized Parking Closures due to Campus Paving October 6, 2021

On Friday October 8 through Monday October 11 there will be multiple parking spot closures due to paving in a number of locations around the university. (Rain dates for paving will be Friday October 22, and Saturday October 23.) Friday 10/8 – Morning of Monday October 11: Lot A / Dowden Hall Parking Lot will […]

Read Story Parking Closures due to Campus Paving
Uncategorized Updates for week of Aug. 1 – 9, 2021 July 30, 2021

Starting August 1 through August 8, Wasylean parking lot (Lot B) will be offline except for emergency and campus police vehicular traffic.   Starting August 2 through August 21, there will be no parking along the LRC/Student Center roadway.  Deliveries to the Student Center and LRC loading docks will be restricted to box trucks only.   Starting […]

Read Story Updates for week of Aug. 1 – 9, 2021